Part 1 of our building project is here.
The builders Jones and Maher of Carmarthen have continued demolishing the interior of the house and by the first week in July they had inserted the new structural steelwork to support the new mezzanine level and where we are extending our bedroom into the existing bathroom (which is really too large).
John tends to see Phil the site foreman most days and we’re pretty sure that he (Phil) now thinks that he has a client with OCD. We’ve spent the best part of a year planning this work to include the extensions, underfloor heating, increased insulation in the floors and vaulted roof, solar hot water, and a new kitchen (as we are relocating some of the old one into the utility room). So getting is a ‘right’ as possible is one of our main aims.
Much of our time is spent just trying to think ahead; for instance it is necessary to decide on the floor finishes as the finished floor heights for the extensions will need to be calculated taking these into account. As the windows and front doors are being ordered from Rationel, a Danish company (with manufacturing plant in Poland) and come pre finished it is necessary to decide on colours at the outset; so that they can be ordered in advance to arrive at the correct time.
Of course having decided to start work in summer the weather has remained extremely wet, which hasn’t helped with digging the foundations for the new extensions.
The new concrete is then ‘tied’ to the existing footings by inserting and resin bonding steel bar into the original concrete foundations.